Cross-Border Electricity Trade (CBTE)
How India Trades Power with Its Neighbours
Cross-border electricity trade (CBTE) means one country selling electricity to another country through power lines that cross the border. India buys electricity from Nepal and Bhutan, sells electricity to Bangladesh, Nepal and Myanmar, and even lets Nepal send power to Bangladesh through Indian lines. The whole trade is controlled by a set of rules made by India's Ministry of Power, called the Guidelines for Import/Export (Cross Border) of Electricity, 2018. For South Asia, it is one of the most practical ways to share resources across borders.
Why does it exist?
Different countries have different kinds of energy. Nepal and Bhutan have fast mountain rivers, which are ideal for hydropower. India has a huge demand for electricity and a big grid (the network of power lines that carries electricity around the country). Bangladesh is short of power. Trade lets each country use what the others have. A simple comparison: it is like a farmer with extra milk selling it to a neighbour who has extra grain, so both families eat better.
Why does timing matter?
Hydropower in Nepal is plentiful in the monsoon (June to October), when rivers are full. In winter, river flow drops and Nepal may even need to buy power from India. So the two grids help each other at different times of the year. Nepal sells its extra monsoon power to India and buys from India in the dry season. Without trade, Nepal would waste its extra monsoon water, a problem called "spilling" of energy.
Where did it come from?
The trade started small and grew step by step:
- India began helping Bhutan build hydropower projects in the 1960s and 1970s. The Chukha project (336 MW) was the first big one, and its surplus power was sold to India. India-Bhutan hydropower is still the oldest and largest example of CBTE in South Asia.
- India and Nepal have exchanged small amounts of power along the border for decades.
- In October 2014, India and Nepal signed the Agreement on Electric Power Trade, Cross-Border Transmission Interconnection and Grid Connectivity. It is often called the Power Trade Agreement (PTA). It allowed electricity trade on commercial terms between companies, not only between governments.
- In November 2014, the SAARC countries signed the SAARC Framework Agreement for Energy Cooperation (Electricity) at the Kathmandu summit.
- In December 2018, India's Ministry of Power issued the Guidelines for Import/Export (Cross Border) of Electricity, 2018. In 2019, the Central Electricity Regulatory Commission (CERC) made its own regulations on cross-border trade.
- On 4 January 2024, India and Nepal signed a long-term agreement under which India aims to import up to 10,000 MW of electricity from Nepal over the next ten years.
- On 3 October 2024, Nepal, India and Bangladesh signed a three-country agreement. Under it, Nepal sends 40 MW to Bangladesh through Indian transmission lines. The first such power flowed on 15 November 2024. It was the first three-country power trade in South Asia.
How does the 2018 framework work?
The main rule is simple: no one can import or export electricity across India's borders without approval from a Designated Authority.
- The Ministry of Power named a senior member of the Central Electricity Authority (CEA) as the Designated Authority. The CEA is India's main technical body for the power sector.
- Any company that wants to trade, Indian or from a neighbouring country, applies to the Designated Authority with details of the power plant, the quantity and the time period.
- Once approved, the power can be sold in three ways: through a government-to-government deal, through a long-term or short-term contract between companies, or through India's power exchanges.
- The CERC, India's central power regulator, makes the rules on prices, grid charges and settlement for this trade.
What is a power exchange?
A power exchange is like a vegetable market for electricity. Sellers offer power, buyers bid for it, and a price is set for each time block, usually for the next day. India's biggest is the Indian Energy Exchange (IEX). Since November 2021, Nepal has been selling some of its power directly on the Indian exchanges after approval from the Designated Authority.
In July 2023, the CEA changed its procedure so that an Indian trading company can trade on the exchanges on behalf of a neighbouring country's company, within a fixed quantity and period. This applies only where that country has a power cooperation agreement with India.
How does the power physically travel?
Electricity moves through high-voltage transmission lines.
- The main India-Nepal link is the Dhalkebar-Muzaffarpur 400 kV line, which joins Dhalkebar in Nepal to Muzaffarpur in Bihar. It was first used in 2016. As of July 2026, the two sides agreed to let up to 1,650 MW flow from Nepal to India and up to 1,400 MW from India to Nepal on it.
- More 400 kV lines are being built or planned, such as New Butwal-Gorakhpur (Uttar Pradesh).
- India and Bangladesh are linked through the Baharampur (West Bengal) to Bheramara (Bangladesh) connection. The Nepal-to-Bangladesh power also uses this route.
- Bhutan's hydropower comes into India's grid through lines into West Bengal and Assam.
Key changes made in 2024
In August 2024, the Ministry of Power amended the 2018 guidelines. One change allows an Indian power plant that supplies its whole output to a neighbouring country to be connected to the Indian grid. This helps such a plant keep selling power inside India if the foreign buyer stops paying or stops buying. The Godda plant in Jharkhand, built to supply power only to Bangladesh, is the best-known example of such a plant.
India's position and Indian examples
- Bhutan: India buys surplus power from India-built projects such as Chukha, Kurichhu, Tala and Mangdechhu. Hydropower sales are one of Bhutan's biggest sources of income.
- Nepal: Indian companies are building big hydropower projects in Nepal. SJVN (a central public sector company) is building the 900 MW Arun-3 project. The approved quantity of Nepal's exports to India has been rising year after year.
- Bangladesh: India is a major supplier of electricity to Bangladesh, through both public sector deals and the Godda plant.
- Myanmar: India supplies small amounts of power to border areas of Myanmar.
- The wider vision: India's idea of One Sun One World One Grid (OSOWOG), first proposed in 2018 at the International Solar Alliance, imagines solar power traded across many countries and time zones. BIMSTEC countries also signed an MoU on grid interconnection in 2018.
Commonly confused concepts
- CEA vs CERC: The CEA (Central Electricity Authority) is the technical planning body; its member acts as the Designated Authority that approves each cross-border trade. The CERC (Central Electricity Regulatory Commission) is the regulator that sets prices, charges and market rules. Both are set up under the Electricity Act, 2003.
- Import vs export: India imports power from Nepal and Bhutan and exports power to Bangladesh, Myanmar and also Nepal (in winter). India-Nepal trade flows both ways depending on the season.
- Bilateral vs trilateral trade: India-Nepal trade is bilateral (two countries). The Nepal-India-Bangladesh deal is trilateral: Nepal sells to Bangladesh, and India only provides the "road" (its transmission lines).
- Mahakali Treaty vs Power Trade Agreement: The Mahakali Treaty (1996) is about sharing the water of the Mahakali river and the planned Pancheshwar dam. The 2014 PTA is about buying and selling electricity. They are separate agreements.
- Installed capacity vs approved export: Installed capacity is how much a plant can produce. Approved export is how much India has allowed to be sold across the border. They are different numbers.
Issues, criticism and the way forward
- Approval delays: Nepali developers say approvals for each project take time and come in small amounts. India says approvals depend on technical checks and grid capacity.
- Ownership concerns: India is careful about buying power from plants built or funded by companies from countries it has strategic concerns about. Reports from Nepal say this has slowed approvals for some projects.
- Weak transmission: Only a few high-capacity lines cross the border. Without more lines, more power cannot flow, even if both sides agree to trade.
- Seasonal mismatch: Nepal has extra power mainly in the monsoon. India's demand peaks in summer and evenings. Storage and better planning can reduce this gap.
- Long project times: Big hydropower projects take many years and face floods, landslides and local protests.
- Way forward: Experts suggest faster and longer approvals, more cross-border lines, a regional power market for South Asia, and using BIMSTEC and the BBIN (Bangladesh, Bhutan, India, Nepal) framework to plan the grid together.
Concepts to Know
- Megawatt (MW): A unit that measures how much electricity can be produced or carried at one moment. 1,000 MW = 1 gigawatt (GW). A 900 MW plant can power a large city.
- Grid: The connected network of power plants, high-voltage lines and substations that carries electricity from where it is made to where it is used.
- kV (kilovolt): A measure of the voltage of a power line. Higher voltage lines, like 400 kV, can carry much more power over long distances.
- Hydropower: Electricity made by using the force of flowing or falling water to turn turbines.
- Designated Authority: The official in India who must approve every import or export of electricity across the border.
- Power trading company: A licensed company that buys power from sellers and sells it to buyers, like a wholesaler.
- Guidelines for Import/Export (Cross Border) of Electricity issued by the Ministry of Power in December 2018; amended in August 2024
- Designated Authority: a Member of the Central Electricity Authority (CEA)
- CERC made cross-border trade regulations in 2019
- India-Nepal Power Trade Agreement: October 2014
- SAARC Framework Agreement for Energy Cooperation (Electricity): November 2014, Kathmandu
- India-Nepal long-term agreement: 4 January 2024, target of up to 10,000 MW imports by India over 10 years
- Nepal-India-Bangladesh trilateral deal: 3 October 2024; 40 MW; first flow 15 November 2024
- Main India-Nepal line: Dhalkebar-Muzaffarpur 400 kV; agreed limits as of July 2026: up to 1,650 MW Nepal to India, up to 1,400 MW India to Nepal
- Nepal sells power on Indian power exchanges since November 2021